Before plastering, ask your electrician for a neutral wire and a deep back box at every switch, Cat6 cable to every camera, access point and TV position, empty conduits to the gate, roof tank and windows, a network cabinet on its own circuit, and a distribution board with spare ways and a surge protector.
The most expensive week in your build
There is a week in every Nigerian building project when the walls are blocked, the conduits are chased in, and the plasterers are waiting. Whatever cables are in the walls that week will be there for the next 30 years.
Mr Okafor learned this the hard way. He built a beautiful five-bedroom house in Enugu while living in Houston. Two years later he wanted cameras, smart lighting and remote gate control. The installer found no neutral wires at the switches, no cable route to the gate and no way to reach the roof tank. The retrofit meant chasing finished walls, repainting three rooms and running surface trunking up the staircase.
None of it would have been necessary if a single page of instructions had reached the electrician before the plaster went on. This article is that page.
You do not need to install any smart devices now. You only need the house to be ready for them. The cables and boxes cost little during construction; adding them later costs far more.
Mains power: six things to specify
1. A neutral wire at every switch box. Most smart switches need a neutral to power themselves. Traditional Nigerian wiring often brings only the live ("loop") to the switch. Ask for the neutral to be brought to every switch box, even if you install ordinary switches for now.
2. Deep back boxes. Smart switch modules sit behind the switch plate. Specify deeper boxes (commonly 35–47 mm) at every switch position so modules fit without forcing.
3. Separate circuits for heavy loads. Give each AC, water heater and pumping machine its own circuit and breaker. This lets a smart relay or contactor control each one later, and lets an energy monitor see each one separately.
4. A distribution board with room to grow. Ask for at least 30% spare ways, space for a surge protective device, and room around the incoming cables for an energy monitor's current clamp.
5. Clear changeover planning. Plan the inverter, generator and grid changeover from the start, and decide which circuits are "essential" (fridge, lights, network, security) and which are not. Wire them on separate sections of the board so automation can shed load cleanly.
6. Power where future devices will sit. Sockets or fused spurs at window heads for motorised curtains, at the gate pillar for the gate motor and intercom, in the ceiling of the main corridor for a hub or access point, and in the roof space for tank equipment.
Network and low-voltage: eight things to specify
Low-voltage cabling is the nervous system of a smart home. It is cheap during construction and painful afterwards.
7. A network cabinet. Choose one central, ventilated spot (often a store under the stairs) where all data cables end. Give it a dedicated circuit fed from the essential side of the board, so the router, hub and camera recorder stay on through every changeover.
8. Cat6 to every camera position. Wired IP cameras powered over Ethernet (PoE) are more reliable than Wi-Fi cameras and need only one cable each. Mark camera positions on the drawing: gate, driveway, each external door, the back of the compound and the generator house.
9. Cat6 to Wi-Fi access point positions. Thick block walls and concrete floors weaken Wi-Fi badly. A ceiling access point on each floor, wired back to the cabinet, gives far better coverage than a single router.
10. Cat6 to every TV wall and home office. Streaming and video calls are more stable on cable.
11. An empty conduit to the gate. The gate motor, intercom, gate camera and access keypad all need power and data at the gate. Lay at least one spare conduit from the house to the gate pillar, with a draw wire inside.
12. Conduits to the roof tank and borehole. A tank level sensor and pump controller need a cable route. Lay a small conduit to the tank stand and the borehole or pump house.
13. Sensor cables at doors and windows (optional). Wired door contacts are the most reliable alarm sensors. If you plan a full alarm, run thin alarm cable to each external door and ground-floor window. Wireless sensors are a fine alternative if you skip this.
14. Separate low-voltage from mains. Data cables should run in their own conduits, not alongside mains cables, to avoid interference and for safety.
The one-page brief for your electrician
Print this, sign it and hand it over before the conduits are closed. Ask for photographs of every wall before plastering.
| AREA | INSTRUCTION |
|---|---|
| Switches | Neutral to every switch box; deep back boxes throughout |
| Heavy loads | Separate circuit and breaker for each AC, water heater and pump |
| Distribution board | 30% spare ways; space for surge protector and energy monitor clamp |
| Essential circuits | Fridge, lights, network cabinet and security on a separate essential section |
| Network cabinet | Central, ventilated; dedicated essential circuit |
| Cat6 | To each camera, each access point, each TV wall and office; all home-run to the cabinet |
| Gate | Spare conduit with draw wire from house to gate pillar; power at the pillar |
| Tank and pump | Small conduit to tank stand and pump house |
| Windows | Power at window heads where curtains may be motorised |
| Separation | Data and mains in separate conduits |
| Records | Photograph every wall before plaster; label all cables at both ends |
This page usually adds a modest amount to the electrical budget. Compared with chasing finished walls later, it is one of the best-value decisions in the whole build.
Pre-plaster checklist
- Neutral wire confirmed at every switch box
- Deep back boxes fitted at all switch positions
- Separate circuits for every AC, heater and pump
- Distribution board sized with spare ways and surge protector space
- Essential and non-essential circuits separated
- Network cabinet location agreed and powered
- Cat6 runs pulled to all cameras, access points, TVs and office
- Spare conduit with draw wire to the gate pillar
- Conduits to roof tank and pump house
- Power at window heads for future curtains
- Data and mains in separate conduits
- Every wall photographed and every cable labelled
Related guides
- How Much Does It Cost to Automate a Home in Lagos? (2026 Cost Breakdown)
- Building in Nigeria from Abroad: How Diaspora Owners Monitor Construction and Property Remotely
- The Neutral Wire Problem: Why Smart Switches Fail in Older Nigerian Houses (and 5 Ways to Fix It)
- Generator Automation Explained: ATS Changeover, Auto-Start and Fuel Monitoring for Nigerian Homes
- Smart Gate Automation in Nigeria: Sliding vs Swing Motors, Solar Backup and Real Costs
- The Smart Estate Blueprint: What Nigerian Developers Should Build In from Day One
Final word
A smart home starts long before the first smart switch is installed. It starts with a wire in the wall that most people never think about.
If you are building now, take this page to site this week. If you are building from abroad, send it to your project manager and ask for photographs before plaster. Ten minutes of planning now can save weeks of disruption later.
Building in Lagos or elsewhere in Nigeria? LiveSmart Realty NG reviews electrical drawings and produces smart-ready wiring specifications for homeowners, architects and developers. Send us your drawings
Frequently asked questions
Do I need to install smart devices during construction?
No. You only need the wiring and boxes in place. Devices can be added room by room after you move in.
What is a neutral wire and why does it matter?
The neutral completes the electrical circuit. Smart switches use it to power their electronics. Without it at the switch box, your choice of smart switches is limited.
Is Wi-Fi enough, or do I need Cat6?
For phones and laptops, good Wi-Fi is fine. For cameras, access points and TVs, cable is far more reliable, especially through thick Nigerian block walls.
How much does pre-wiring add to my budget?
Usually a small share of the electrical budget, mainly cable, conduits and extra boxes. It is far cheaper than retrofitting later, which commonly adds 15–30% to labour.
My house is already plastered. Is it too late?
No. Retrofit is very possible with wireless modules, battery sensors and careful cable routing. It simply costs more labour.
Should my architect be involved?
Ideally yes. Camera positions, curtain pockets, network cabinet space and gate cabling are easier to design on the drawings than to improvise on site.